This Thursday night (30th March 2023) we will be carrying some investigations on the bridge using a convoy of vehicles. This is so we can measure how the bridge reacts under this load and is part of a planned inspection and maintenance program. .
The convoy of vehicles will travel across the bridge and at set points specialist measuring equipment will tell our team what is happening. This data will then be processed and will be used as part of the future inspection and maintenance program.
The work will be carried out late on Thursday night, when traffic is minimal, and will require a single lane at a time. This means that you will be able to cross the Bridge as normal. However, if you are using the Bridge on Thursday night, please keep an eye out for these slow moving vehicles.